August – Planning began to address DNR Nutrient Reduction Strategy Requirements.
August – November – Completed Future Wastewater Treatment Plant Site Selection Process – Purchased Selected Site.
September 2018 – February 2019 – Completed Future Wastewater Treatment Plant Site Selection Process – Purchased Selected Site.
June – Initial submittal of design loads to Department of Natural Resources (DNR).
October – City Council approves plant load with 25% reserve unallocated capacity for future.
December – Secure State Revolving Loan for Planning and Design Work needed.