Contractor, Woodruff Construction will tentatively have their crew start mobilizing to the site (locations identified in pictures) on Monday, April 24, 2023, in preparation to begin this project.
The project will consist of removal of existing concrete trail, surface adjustment to meet grade, 3” compactable material for pit run, 4” PCC concrete for trail tying to existing panels, surface restoration including seeding.
Last modified: April 24, 2023